SJR Insultech on Danish television
Denemarken, 10 March 2020 -A number of years ago, SJR Insultech carried out insulation work within phase 1 of a biogas plant in Ringe, Denmark. The activities involved insulating three 9,000-m³ biogas tanks and cladding them with profile panels.
At present, SJR Insultech is working on phase 2 of this plant. In this phase, SJR will be insulating three 10,000-m³ biogas tanks and cladding them with profile panels.
This project has been featured on Danish television, which covered a site visit by the Minister of Climate and Energy Dan Jørgensen. This report clearly shows the work carried out by SJR Insultech, since some of the tanks had not yet been insulated at the time of recording.